Vonda L. Thomas Posted October 29, 2020 Report Share Posted October 29, 2020 Presented with an out of scope/Cardinal change to an existing Contract that was procured as a Sole Source. Is the original Sole Source determination sufficient to cover all requirements/activities under the contract? Note the out of scope work will likely be justified as sole source as well. Link to comment Share on other sites More sharing options...
Neil Roberts Posted October 29, 2020 Report Share Posted October 29, 2020 FAR 6.001 might provide an answer for you. Link to comment Share on other sites More sharing options...
Neil Roberts Posted October 29, 2020 Report Share Posted October 29, 2020 Then, FAR 6.302-1 Link to comment Share on other sites More sharing options...
joel hoffman Posted October 30, 2020 Report Share Posted October 30, 2020 If this is a Part 19 sole source contract, then it might be added using an out of scope sole source, supplemental agreement for administrative purposes. 6.302-5 Authorized or Required by Statute Link to comment Share on other sites More sharing options...
Recommended Posts