Jump to content
The Wifcon Forums and Blogs

Recommended Posts

c) If the Contractor does not have an approved purchasing system,  consent to subcontract is required for any  subcontract that - 

[...]

(2) Is fixed-price and exceeds - [...]

(ii) For a contract awarded by a civilian agency other than the Coast Guard and the National Aeronautics and Space Administration, either the simplified acquisition threshold, as defined in FAR 2.101 on the date of  subcontract award, or 5 percent of the total estimated cost of the contract.

Which one applies?  The SAT or 5% of the total contract cost?  I always thought that consent is required for Fixed Price Subontracts which exceed SAT.  What if the total contract is at $70 MIL of estimated cost.  Would consent be required at $250,000 or at $3.5MIL?  It does not say "greater of" or "lesser of"

It is the same issue with Alternate I for notifications for fixed price subcontracts.   Thanks as always. 

Link to post
Share on other sites
14 hours ago, Tzarina of Compliance said:

Which one applies?  The SAT or 5% of the total contract cost?

Both. Read it as either or. In other words, it’s required if either condition or both conditions are met.

Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...