LearnMeAContract Posted August 31, 2020 Report Share Posted August 31, 2020 Is CCPD required for a modification that is increasing the value (by less than SAT) of a multi-million dollar IDIQ contract that already exceeded the TINA threshold and was required CCPD at the time of the Base Award? Note: Not a commercially available item. hypothetical example: Base Award Contract Value was $5M CCPD was obtained for it at that time. Mod is for $65K increase. Total Contract value after mod award would be $5,065,000. Link to comment Share on other sites More sharing options...
Don Mansfield Posted August 31, 2020 Report Share Posted August 31, 2020 The contracting officer would actually be prohibited by FAR 15.403-1(a) from obtaining CCPD. This assumes that the mod is only for an increase--not a net increase after addition and subtraction. Link to comment Share on other sites More sharing options...