Recently my office is having a lively debate regarding the DD2579, specifically block "10j". 

Side #1

If your requirement is a Task Order off of a SATOC would it be appropriate to select "multiple award" then subsequently "Delivery/Task Order".  The argument basically stems from the "SA" in SATOC stands for Single Award...how could selecting "multiple award be appropriate"? 

Side #2

Some of the COs feel that they are misrepresenting their recommendation if they select "multiple award".  After all they are only requesting a Task Order.  Therefor any TO SATOC or MATOC they do not select that button (10j)

Side #3

Why does Small business Office even care if it is a TO or not? 

 