brad Posted June 1, 2020 Report Share Posted June 1, 2020 Can the contracting officer update FAR thresholds on existing contracts? for example... the micro was at 3k at award but is now 10k? Link to comment Share on other sites More sharing options...
ji20874 Posted June 2, 2020 Report Share Posted June 2, 2020 I don't understand the question. If the purchase order (contract) is already awarded, leave it alone. Thresholds such as the micro-purchase threshold apply in pre-award situations (before contracts are awarded) to settle on clauses, competition requirements, and so forth -- all of which is water under the bridge once the contract is awarded. Leave it alone, and enforce it as it is written and as it was agreed to. Link to comment Share on other sites More sharing options...