Firm Fixed Price Level of Effort


Recommended Posts

My company is responding to a solicitation.  The KO has issued a clarification that the contract

  1. Any order awarded under this solicitation would be  Fixed Priced Level of Effort and would not be Firm Fixed Price. The hours would be billed as they are worked and separated out in each invoice.

 

In reviewing, 16.207, I don't understand how 16.201-1(b) applies.  Do we get the Fixed Price regardless of LOE delivered (at the end)?  (This seems to contradict the instructions from the KO above). Or do we only get a unit price per hour worked?  If we provide the LOE does the contract end? Or like an ordinary FFP, do we still need to work to complete the POP?

 

 

Link to comment
Share on other sites

It is very possible that the contracting officer does not understand FFP-LOE.  However, we don't understand much about your situation, as you haven't offered much.

How is the solicitation's bid schedule set up?  For example, 1 JB, or 6 MO, or 5,000 HR?

What is the solicitation asking for?  A product?  A report?  Employee hours?

Does the solicitation specify a level of effort?  Are you supposed to specify a level of effort in your proposal?

Link to comment
Share on other sites

Guest PepeTheFrog

PepeTheFrog doesn't know if this applies to this scenario, but suspects that it might. Here's a magic trick.

The FAR and other guidance strongly discourages the use of labor hour (time and materials) contracts. Lots of paperwork and oversight!

So, you take a "Fixed Price Level of Effort" (?) contract. The contract "hours would be billed as they are worked and separated out in each invoice." The contractor invoices said hours each month.

By magic, you have something that resembles, in some ways, a labor hours contract. But you don't have to worry about as much paperwork and oversight! No, it's a "Fixed Price Level of Effort" contract. Well, OK.

PepeTheFrog is not endorsing this whatsoever, just pointing out that it happens. 

PepeTheFrog also shares @ji20874 suspicion that perhaps the contracting officer doesn't understand FFP-LOE. 

Link to comment
Share on other sites

Thank you for attempting answers with the small amount of information I left. 

It is for services Base + 4 options and a specific # of hours per labor category was specified.

This is a recompete and the previous contract was FFP.  Also, until this specific direction from the KO, we thought it was FFP.

So do we get to bill the full FFP amount or are we invoicing only based on hours worked? 

 

 

Link to comment
Share on other sites

How is the solicitation's bid schedule set up?  For example, 1 JB, or 6 MO, or 5,000 HR?

  • _______________.

What is the solicitation asking for?  A product?  A report?  Employee hours?

  • Services.

Does the solicitation specify a level of effort?  Are you supposed to specify a level of effort in your proposal?

  • The solicitation specifies the level of effort.

You really need to answer the first question before I can be helpful. 

Link to comment
Share on other sites

So, something like--

Item   Supplies/Services   Qty   Unit     Unit Price     Amount

001     LCAT 1                  100  HR     $__________  $__________

001     LCAT 2                  800  HR     $__________  $__________

003     LCAT 3                  400  HR     $__________  $__________

Link to comment
Share on other sites

This really doesn't seem like a FFP-LOE approach as contemplated by FAR 16.207; rather, it seems like a FFP approach as contemplated by FAR 16.202. 

It seems that this is a plain, ordinary FFP approach, with the unit denominated in hours.  You will be paid the FFP for each hour authorized by the Government, up to a total of 2008 HRs.  The QTY is an estimated quantity, or maybe a ceiling quantity.

Link to comment
Share on other sites

If you get get selected to negotiate consider the possibility of having them annotate the CLIN schedule with hours as "estimated" and propose a clause like FAR 52.211-18 for inclusion in the contract.  While used in construction I have seen it used in service contracts.  

Link to comment
Share on other sites