Jump to content

Change order for delivery


Recommended Posts

GFP no longer required on a contract must be delivered for usage on a different contract (by a different contractor).

There is no delivery/shipping CLIN in the Schedule.

May the CO issue a change order to create this CLIN, an NTE price for 1 Lot, and specify its delivery instructions IAW clause 52.243-1 Changes-Fixed-Price?

 

 

Link to comment
Share on other sites

7 minutes ago, ji20874 said:

No.  Read para. (a) of the Changes clause.

You're dealing with government property, right?  Have you read the Government Property clause of the contract?

Yes. I see now, I think. No need for a new CLIN. Issue a unilateral mod citing the 52.245-1 directing delivery/return of the GFP . Then, as the clause states, settle on an equitable adjustment for the GFP delivery.

That's my interpretation. Am I reading correct?

Link to comment
Share on other sites

Right.  Para. (d)(3) of the Government Property clause gives you the authority to do whatever you need to do.

The notice to return the GFP is just a notice -- it could be by letter -- a modification is not needed for the notice.

The equitable adjustment afterwards could involve a modification and a new CLIN.

Link to comment
Share on other sites

Ah, the authority for the Mod on SF30 would then be the Government property clause...just sayin’....  :)

Link to comment
Share on other sites

Guest
This topic is now closed to further replies.
×
×
  • Create New...