Sunstrider Posted April 4, 2019 Report Share Posted April 4, 2019 GFP no longer required on a contract must be delivered for usage on a different contract (by a different contractor). There is no delivery/shipping CLIN in the Schedule. May the CO issue a change order to create this CLIN, an NTE price for 1 Lot, and specify its delivery instructions IAW clause 52.243-1 Changes-Fixed-Price? Link to comment Share on other sites More sharing options...
ji20874 Posted April 5, 2019 Report Share Posted April 5, 2019 No. Read para. (a) of the Changes clause. You're dealing with government property, right? Have you read the Government Property clause of the contract? Link to comment Share on other sites More sharing options...
Sunstrider Posted April 5, 2019 Author Report Share Posted April 5, 2019 7 minutes ago, ji20874 said: No. Read para. (a) of the Changes clause. You're dealing with government property, right? Have you read the Government Property clause of the contract? Yes. I see now, I think. No need for a new CLIN. Issue a unilateral mod citing the 52.245-1 directing delivery/return of the GFP . Then, as the clause states, settle on an equitable adjustment for the GFP delivery. That's my interpretation. Am I reading correct? Link to comment Share on other sites More sharing options...
ji20874 Posted April 5, 2019 Report Share Posted April 5, 2019 Right. Para. (d)(3) of the Government Property clause gives you the authority to do whatever you need to do. The notice to return the GFP is just a notice -- it could be by letter -- a modification is not needed for the notice. The equitable adjustment afterwards could involve a modification and a new CLIN. Link to comment Share on other sites More sharing options...
joel hoffman Posted April 5, 2019 Report Share Posted April 5, 2019 Ah, the authority for the Mod on SF30 would then be the Government property clause...just sayin’.... Link to comment Share on other sites More sharing options...
Sunstrider Posted April 5, 2019 Author Report Share Posted April 5, 2019 Thank you both! Link to comment Share on other sites More sharing options...