Price Negotiation Memorandum, and Contractors access to it


sprice11

Recommended Posts

I have requested the Price Negotiation Memorandum's for multiple  Contracts/Delivery Orders from our Contracting Officer.  They said that they are not able to provide us with the documents.  Does anybody know if it is possible for the Contractor to obtain this information from the government?  

 

I have asked for it because it would show that the Contracting Officer has found our price/cost to be fair and reasonable.  

Link to comment
Share on other sites

Are you in a pre-contract mode or have the contracts/orders been issued?  If pre-contract, the government may be asserting that they are pre-decisional and cannot be released at this time.  On the other hand, if the contracts have been awarded, I see no reason why they cannot be released.  I know they are available through discovery in litigation without a protective order.

Link to comment
Share on other sites

The PNM is an internal pre-decisional Government document, and I would assert that it is privileged from release under FOIA.

You want proof that your cost/price is fair and reasonable?  The mere fact that the contract was awarded at that cost/price is proof that the contracting officer found the cost/price to be reasonable.

Link to comment
Share on other sites

49 minutes ago, ji20874 said:

You want proof that your cost/price is fair and reasonable?  The mere fact that the contract was awarded at that cost/price is proof that the contracting officer found the cost/price to be reasonable.

That is a correct statement.  However, DCAA frequently questions costs that were specifically negotiated prior to contract award.  This is particularly true with regard to labor rates.  In this regard, I can see why a contractor would want to obtain a PNM to support the reasonableness of costs.

If the contract has been awarded, what harm is there in releasing the PNM to the contractor covered by the PNM?  After all, the contractor was a party to the contract award process.  Under current FOIA doctrine promoting transparency of government operations, if there is no harm to the government or a third party from release of a document, that document should be released even if it does technically fall within a FOIA exception.

Link to comment
Share on other sites

The Contract, and multiple negotiated Delivery Orders against the contract have already been awarded.  Retreadfed is correct in that DCAA is the one questioning fair and reasonableness of negotiated costs.  I did use the fact that the contract was awarded as my basis for saying costs were already determined to be fair and reasonable.  However, now even the Contracting Officer is taking DCAA's side.  It is a very interesting discussion we are having with both DCAA/DCMA/PCO....

We were not given a reason why they cant release it to us....So Im guessing FOIA would be the next step.  Thanks for the information. 

Link to comment
Share on other sites

Well, then, ask for the PNM under FOIA.

Let us know if you do or do not get it.

But you might be barking up the wrong tree.  You must not conflate the overall estimated cost (or price) of the contract (which is found reasonable at the time of contract formation) and the incurred costs for any individual parts or pieces of the contract (which are found allowable during contract performance).  That the contracting officer found the overall estimated cost to be reasonable (explained in the PNM) does not mean that any or all incurred costs are allowable for reimbursement during contract performance.  So to me, any incurred cost may most certainly be challenged during contract administration, and the PNM is irrelevant to that challenge of proving allowability.  The burden is on the contractor to prove the allowability (incl. reasonableness) of any and all incurred costs during contract administration (absent any pre-contract cost advance agreement (FAR 31.109)).

On 1/24/2019 at 9:29 PM, sprice11 said:

DCAA is the one questioning fair and reasonableness of negotiated costs.

 

Really?  Is DCAA questioning the established estimated cost of the contract, or is DCAA actually questioning incurred costs?  I suspect it is the latter.

Edited by ji20874
change pre-contract cost agreement to advance agreement
Link to comment
Share on other sites

ji, in my experience, specific areas of cost, such as labor rates, are negotiated prior to the award of a contract.  As a result, the PNM addresses those costs and explains why they were determined to be reasonable and accepted.  If those same labor rates are used in contract performance, the PNM is evidence of the reasonableness of those labor rates. 

Link to comment
Share on other sites

I'm getting the sense that the OP has not provided us with sufficient info to help out. Apparently there is an ID/IQ with multiple Delivery Orders.

What is the contract type of the Delivery Orders? CP, FP, T&M -- what?

Is DCAA questioning the D.O. price or something else? Normally, DCAA does not question contract prices unless the auditors are alleging defective pricing. Is DCAA alleging defective pricing?

Is DCAA alleging that the contractor acquired materials in performance of the D.O.'s, and the contractor cannot establish that those prices were fair & reasonable? If the D.O. is CP, then this may be a valid assertion.

So much we don't know; how can we give advice?

Link to comment
Share on other sites

I agree H2H. I started to post this morning with similar questions, then decided that the only question that OP asked was whether they could obtain a copy of a PNM for some unclear objective.  

Years ago we provided copies and asked contractor to sign those over $100,000 (when threshold was $ 100k). That was our local District’s policy.  It should be noted that our pre-negotiation objectives were always separate documents and often consisted of marked up proposals for small changes.

My next District used memoranda of agreement or memoranda of understanding to document mutual understandings and agreements. 

I used those throughout my subsequent career. 

We don’t know what was “negotiated”, whether competitive or non-competitive, what the auditors are questioning, etc. 

For instance, Is it pricing or costs? Post awRd, pre-award, incurred costs, questioned costs, unsupported costs, etc.? 

If they are questioning a negotiated cost, then they would probably be questioning the KO’s basis of settlement.  Of course the KO would have determined something to be fair and reasonable - probably the overall settlement. It may have involve the contracting officer non-concurring with some of the audit results, prior to negotiations.

Who here can know?  

Link to comment
Share on other sites

Now days, when price negotiation memoranda contain details of the prenegotiation objectives, I would say that somebody’s going to have to legally force me to turn over a copy of the overall price negotiation memorandum.

 And then I would redact out my prenegotiation objectives. In this instance, it appears that the contractor wants to know what the contracting officer thought was fair and reasonable. 

Link to comment
Share on other sites

On 1/25/2019 at 9:49 AM, Retreadfed said:

ji, in my experience, specific areas of cost, such as labor rates, are negotiated prior to the award of a contract.  As a result, the PNM addresses those costs and explains why they were determined to be reasonable and accepted.  If those same labor rates are used in contract performance, the PNM is evidence of the reasonableness of those labor rates. 

If specific areas of cost are mutually agreed to before award of the contract, those agreements should be captured in the contract or in a bilateral advance agreement (FAR 31.109) — not in a unilateral PNM.  If the parties talked about specific areas and then did not formalize anything, then there is no agreement.  Remember, a PNM only records one party’s side to a negotiation.

One could say they discussed specific areas solely for understanding and to come to agreement on the overall estimated cost for the contract.

Besides, the contractor should have its own PNM with its own objectives and understandings of the give-and-take and final negotiated result.

I wholly object to releasing PNMs to contractors.

if the contractor wants an advance agreement covering treatment of certain costs, it should insist on one.

Link to comment
Share on other sites

Guest PepeTheFrog
1 hour ago, ji20874 said:

Besides, the contractor should have its own PNM with its own objectives and understandings of the give-and-take and final negotiated result.

ji20874: Did you do this when you were a contractor? 

Current contractors: Do you do this?

Link to comment
Share on other sites

Sprice, I presume you have an attorney.  If you are dealing with a DoD contract, have him/her look at 32 CFR 97, particularly the definition of "litigation" and DoD policy on release of official DoD information.  Also, read FAR 33.204 and ask him/her to advise accordingly.

Link to comment
Share on other sites

19 hours ago, ji20874 said:

Well, then, ask for the PNM under FOIA.

Let us know if you do or do not get it.

But you might be barking up the wrong tree.  You must not conflate the estimated cost (or price) of the contract (found reasonable at the time of contract formation) and the incurred costs for any individual parts or pieces of the contract (found reasonable during contract performance).  That the contracting officer found the overall estimated cost to be reasonable (explained in the PNM) does not mean that any or all incurred costs are reasonable for reimbursement during contract performance.  So to me, any incurred cost may most certainly be challenged during contract administration, and the PNM is irrelevant to that challenge.  The burden is on the contractor to prove the reasonableness of any and all incurred costs during contract administration (absent any pre-contract cost agreement).

Really?  Is DCAA questioning the established estimated cost of the contract, or is DCAA actually questioning incurred costs?  I suspect it is the latter.

JJ, first off, thanks for your replies.  However, I do disagree with you here.  1) The contracting officer found that our estimated costs to be fair and reasonable.  Meaning we provided them the exact methodology we would be using to when billing the costs that DCAA has since found to be "unreasonable".  2) yes, the burden is on the contractor to provide that any an all costs are reasonable.  We have done so.  We have done so b y showing other contractors charge the same or more for similar "incentives", have done so by showing that the contracting officer/DCAA has found these costs to be reasonable going back over at least three different contracts, and over 20 Delivery Orders.  We didnt all of a sudden change our methodology.  We provide the company plans and procedures that clearly show these are/have been company policy for years.  3) Finally, DCAA is questioning the incurred cost, and questioning the costs based on something that is not in our contract (DSSR).

Now, I could understand if our incurred cost differed wildly, and were incurred in a way inconsistent with our estimated cost.  However, this is not the case.

You also said the following "Remember, a PNM only records one party’s side to a negotiation.".  Well, the PNM must show, as required by FAR 15.406-3 - Documenting the Negotiation "(11) Documentation of fair and reasonable pricing."  -  This is what I am getting at.  We, as a contractor, have no say on this documentation.  The fact they let the contract shows it to be fair and reasonable.

 

 

Link to comment
Share on other sites

7 hours ago, here_2_help said:

I'm getting the sense that the OP has not provided us with sufficient info to help out. Apparently there is an ID/IQ with multiple Delivery Orders.

What is the contract type of the Delivery Orders? CP, FP, T&M -- what?

Is DCAA questioning the D.O. price or something else? Normally, DCAA does not question contract prices unless the auditors are alleging defective pricing. Is DCAA alleging defective pricing?

Is DCAA alleging that the contractor acquired materials in performance of the D.O.'s, and the contractor cannot establish that those prices were fair & reasonable? If the D.O. is CP, then this may be a valid assertion.

So much we don't know; how can we give advice?

Here to help:

 

1) Contract type IDIQ with CPFF Delivery Orders placed against it.

2) DCAA is not alleging defective pricing.  Instead they are questioning costs based on unreasonableness.....which they are basing on a requirement not included in our contract

3) That is all that is being questioned. 

I hope this helps clear up some of your questions.

Link to comment
Share on other sites

6 hours ago, joel hoffman said:

I agree H2H. I started to post this morning with similar questions, then decided that the only question that OP asked was whether they could obtain a copy of a PNM for some unclear objective.  

Years ago we provided copies and asked contractor to sign those over $100,000 (when threshold was $ 100k). That was our local District’s policy.  It should be noted that our pre-negotiation objectives were always separate documents and often consisted of marked up proposals for small changes.

My next District used memoranda of agreement or memoranda of understanding to document mutual understandings and agreements. 

I used those throughout my subsequent career. 

We don’t know what was “negotiated”, whether competitive or non-competitive, what the auditors are questioning, etc. 

For instance, Is it pricing or costs? Post awRd, pre-award, incurred costs, questioned costs, unsupported costs, etc.? 

If they are questioning a negotiated cost, then they would probably be questioning the KO’s basis of settlement.  Of course the KO would have determined something to be fair and reasonable - probably the overall settlement. It may have involve the contracting officer non-concurring with some of the audit results, prior to negotiations.

Who here can know?  

Joel....I just answered some of the questions H2H had.  Now, I can answer some of yours.

1)  non-competitive .  We provided our cost and pricing data, methodologies, etc....technical review was conducted by govt, and seeing as contract was released found to be fair and reasonable

2) It was post award, questioned costs.  And the basis of their questioning the costs is reliant on a regulation that is not in our contract.

That is the reason we are looking for the PNM.  To show that the Contracting Officer found our proposed costs/pricing to be fair and reasonable.  We did not change the way we account for these costs, or incur these costs.....

My question for you now is why would you be reluctant to release the PNM?  You said "And then I would redact out my prenegotiation objectives"...I already have a govt produced spreadsheet showing our position, their position, all counter offers, and the final negotiated amount.  However, this is not the same as a completed PNM.  

Link to comment
Share on other sites

41 minutes ago, sprice11 said:

Here to help:

 

1) Contract type IDIQ with CPFF Delivery Orders placed against it.

2) DCAA is not alleging defective pricing.  Instead they are questioning costs based on unreasonableness.....which they are basing on a requirement not included in our contract

3) That is all that is being questioned. 

I hope this helps clear up some of your questions.

Thanks for the additional information. There have been some recent cases (last 6 months) on cost reasonableness. Are you aware of them?

Additionally, generally all DCAA can do is question a cost (though of course it depends on circumstances). It is normally up to a warranted contracting officer to decide whether or not to sustain the questioned costs. At some point, you need to give up on persuading DCAA to change its position and concentrate, instead, on the contracting officer -- reminding the KO that the price was found to be F&R and what was disclosed, discussed, and agreed-to as part of that finding.

Link to comment
Share on other sites

On 1/25/2019 at 6:03 PM, sprice11 said:

Well, the PNM must show, as required by FAR 15.406-3 - Documenting the Negotiation "(11) Documentation of fair and reasonable pricing."  -  This is what I am getting at.  We, as a contractor, have no say on this documentation.  The fact they let the contract shows it to be fair and reasonable.

 

That's right -- and that's why you don't need the text of the government's PNM to demonstrate that the contract's estimated cost is fair and reasonable.  The contract's bottom-line estimated cost was found fair and reasonable at the time of contract formation.

Now, during contract administration, all of that is irrelevant -- now, during contract administration, you must justify to the contracting officer's satisfaction each incurred cost for which you are seeking reimbursement in that particular voucher (or invoice).

Generally, an incurred cost is determined reasonable AFTER the cost is incurred.  The exception is if the parties have a pre-contract cost an advance agreement (FAR 31.109) -- but it seems you don't have one, so you have to justify the reasonableness of each incurred cost with the voucher where the reimbursement is claimed, amenable to the allowable cost and payment clause of your contract.

You err by conflating (1) the bottom-line estimated cost agreed to at the time of contract formation and (2) incurred costs for which reimbursement is sought during contract administration.  You err in suggesting that the contracting officer, before awarding the contract, already found your [incurred] costs to be reasonable [for reimburement] -- that is impossible, as there were no incurred costs at that time, and generally, incurred costs are determined reasonable after they are incurred.  

Your responsibility now (during contract administration) is to justify the incurred costs included in your most recent voucher for which you are seeking reimbursement.  The Government's PNM is irrelevant.  Follow the allowable cost and payment clause of your contract.  If you are unable or unwilling to do so, the costs must be disallowed.  Pointing to the PNM is irrelevant to the question of cost allowability for reimbursement.

For your next cost-reimbursement contract, maybe you should consider a pre-contract cost an advance agreement.  It is discussed in the FAR and would cover your situation.

Edited by ji20874
change pre-contract cost agreement to advance agreement
Link to comment
Share on other sites

1 hour ago, ji20874 said:

That's right -- and that's why you don't need the text of the government's PNM to demonstrate that the contract's estimated cost is fair and reasonable.  The contract's bottom-line estimated cost was found fair and reasonable at the time of contract formation.

Now, during contract administration, all of that is irrelevant -- now, during contract administration, you must justify to the contracting officer's satisfaction each incurred cost for which you are seeking reimbursement in that particular voucher (or invoice).

Generally, an incurred cost is determined reasonable AFTER the cost is incurred.  The exception is if the parties have a pre-contract cost agreement -- but it seems you don't have one, so you have to justify the reasonableness of each incurred cost with the voucher where the reimbursement is claimed, amenable to the allowable cost and payment clause of your contract.

You err by conflating (1) the bottom-line estimated cost agreed to at the time of contract formation and (2) incurred costs for which reimbursement is sought during contract administration.  You err in suggesting that the contracting officer, before awarding the contract, already found your [incurred] costs to be reasonable [for reimburement] -- that is impossible, as there were no incurred costs at that time, and generally, incurred costs are determined reasonable after they are incurred.  

Your responsibility now (during contract administration) is to justify the incurred costs included in your most recent voucher for which you are seeking reimbursement.  The Government's PNM is irrelevant.  Follow the allowable cost and payment clause of your contract.  If you are unable or unwilling to do so, the costs must be disallowed.  Pointing to the PNM is irrelevant to the question of cost allowability for reimbursement.

For your next cost-reimbursement contract, maybe you should consider a pre-contract cost agreement.  It is discussed in the FAR and would cover your situation.

We have discussed using the pre-contract cost agreement for future contracts/delivery orders.

Now,  how is it that the costs proposed, and the methodologies used to arrive at those costs, followed consistently (FAR when followed exactly as proposed, are somehow now questioned when incurred in the exact fashion as we proposed they would be?   Since cost and pricing data were required, wouldnt FAR 15.404-1(A)(3) apply (ie. evaluate the reasonableness of individual cost elements)?  

Also, payments were never questioned.  All invoices we submitted were paid in full.  The issue is that DCAA, after performing the required yearly audit, has now come back and is questioning reasonableness of the specific costs.  And they are using a regulation that is not included in our contract (DSSR) to base their finding on.

I do appreciate the responses, but I believe that we might have a misunderstanding of what is actually being asked about.   And this may be due to the fact that I am not making myself clear.  

The issue I have is that the Contracting Officer found these costs to be fair and reasonable based on 1) past cost/pricing for same exact services, 2) other contractors offer similar costs.......DCAA didnt say these were expressly unallowable, or say they are unallocable, they say that no reasonable contractor would charge more than the DSSR rate.  Then used the DSSR as a basis for their finding, even though DSSR does not apply/is not required per our contract.

Link to comment
Share on other sites

1 hour ago, here_2_help said:

Thanks for the additional information. There have been some recent cases (last 6 months) on cost reasonableness. Are you aware of them?

Additionally, generally all DCAA can do is question a cost (though of course it depends on circumstances). It is normally up to a warranted contracting officer to decide whether or not to sustain the questioned costs. At some point, you need to give up on persuading DCAA to change its position and concentrate, instead, on the contracting officer -- reminding the KO that the price was found to be F&R and what was disclosed, discussed, and agreed-to as part of that finding.

I have given up on trying to persuade DCAA.  I am now going directly to the PCO/ACO.  However, they seem to be extremely reluctant to go against the advice of another agencies recommendation.  I do truly wish I go into further detail without DOXXING my company/myself.   There have definitely been some quotes by DCAA, and KO that made me wish I recorded the meetings.

Link to comment
Share on other sites

1 hour ago, sprice11 said:

The issue I have is that the Contracting Officer found these costs to be fair and reasonable based on 1) past cost/pricing for same exact services, 2) other contractors offer similar costs.......DCAA didnt say these were expressly unallowable, or say they are unallocable, they say that no reasonable contractor would charge more than the DSSR rate.  Then used the DSSR as a basis for their finding, even though DSSR does not apply/is not required per our contract.

Okay, isn't this basically the same issue as asked in another thread? Now I GET that you weren't asking about the same issue. You asked specifically about the contracting officer's documentation of negotiations. Different vector; same issue. In the other thread I posted an ASBCA opinion that might be relevant to your issue, or perhaps not.

If I were in your situation (and I am, frequently) I would be bringing that ASBCA opinion to the attention of the KO and not-so-subtly suggesting that they go talk to Legal about the likelihood of success when you appeal the COFD. I would be talking about summary judgment, which is typically a cheaper form of litigation. I would be working hard to make the KO realize that the DCAA position was not going to be well regarded by the courts.

Forget the PNM or Negotiation Memo. All that stuff will be discoverable when the appeal is filed. And all those comments you wish you had recorded? You'll get a chance to recite them in your deposition. And the other folks will get a chance to defend their remarks in their deposition, while under oath.

Those are the points I would be making to your KO in trying to resolve this issue now.

Link to comment
Share on other sites

sprice11, I should have said that I would   Not willingly release my pre-negotiation objectives if part of the PNM as is now part of that format (more bureaucratic repetition by requiring a PNO then requiring it to be repeated in the PNM).

At any rate, from the limited information provided, I empathize with your situation. I think you are indicating that there were no oral negotiations, you submitted a detailed prooosal indicating how you were going to pursue the effort, somebody theoretically performed a price and cost analysis and then the KO simply acccepted it.  

Now they are questioning the methodology or the amount of the incurred costs, based upon review by DCAA.

That pre-award ineptitude no longer surprises me, unfortunately. 

In Cost reimbursent contracts, your responsibility is to make a “best effort” to complete the effort within the budget and  time allotted but you don’t guarantee that.

at any rate, you supposedly told them how you were going to pursue the effort, etc., etc., you performed consistent with it, nobody questioned the reasonableness of approach or the amounts during performance and now the DCAA is questioning the reasonableness but not necessarily the allowability of the elements (?).

i agree with H2H.  Good luck.  

 

Link to comment
Share on other sites

Another point -- 16.301-3(4) talks about government surveillance during performance. I would suggest that sprice11 gently ask where that surveillance was, and why no government official ever questioned uplifts in excess of DSSR limits during performance, or during invoice reviews.

Link to comment
Share on other sites

With regard to h2h's ideas maybe this too....noting the imperative "shall".

42.301 -- General.

When a contract is assigned for administration under Subpart 42.2, the contract administration office (CAO) shall perform contract administration functions in accordance with 48 CFR Chapter I, the contract terms, and, unless otherwise agreed to in an interagency agreement (see 42.002), the applicable regulations of the servicing agency.

FAR 42.3 might hold some other gems too!

Link to comment
Share on other sites

On ‎1‎/‎25‎/‎2019 at 7:37 PM, ji20874 said:

Now, during contract administration, all of that is irrelevant -- now, during contract administration, you must justify to the contracting officer's satisfaction each incurred cost for which you are seeking reimbursement in that particular voucher (or invoice).

ji, consider this language from a hypothetical PNM:  "The contractor proposed an hourly labor rate of $X.  We verified this labor rate with DCAA.  Further, this same labor rate was proposed and agreed to under other contemporaneous competitively awarded contracts.  Based on these facts, I have determined that $X per hour is a reasonable amount for the labor proposed."

During contract performance, the contractor paid $X per hour of labor.  Do you believe that this statement from the PNM is not evidence of the reasonableness of the cost incurred during contract performance?

Link to comment
Share on other sites

Guest
This topic is now closed to further replies.
×
×