Sometime in the past 12 months or so, a forum (ASBCA or CoFC, I believe) issued a decision regarding the elements necessary for the allowability of a contractor's pre-contract costs. As I recall, the government argued that specific pre-authorization was required, and the court held otherwise, using a strict reading of FAR 31.205-32. I've drawn a blank trying to remember that decision. Does anybody know of it?

Much appreciated.

Link to comment
Share on other sites

H2H,  is this what you had in mind

Absent an advance agreement, recovery of pre-contract costs requires proof of four elements:  (1) the costs were incurred prior to the effective date of the contract; (2) the costs were incurred directly pursuant to negotiation of the contract and in anticipation of award; (3) the costs were necessarily incurred in order to comply with the proposed contract delivery schedule; and (4) the costs would have been allowable if incurred after the date of the contract.  Radant Technologies, Inc., ASBCA No. 38324, 91-3 BCA ¶ 24,106 at 120,657; FAR 31.205-32. 

The four part test from Radant had been cited in a few later cases.

Link to comment
Share on other sites

Guest
This topic is now closed to further replies.
×
×
  • Create New...