Single Source vs. Sole Source


nkd9

Recommended Posts

Hello all,

Can someone assist with explaining the application of soliciting from a single source pursuant to 13.106-1 (b) vs. sole source acquisition pursuant to 13.501 (a) ? 

Specifically, what does "soliciting from a single source" entail?  How can one comply with posting requirements if only soliciting from one source pursuant to 13.106-1 (b)? 

Mainly, I am trying to understand the difference between the two authorities. 

Link to comment
Share on other sites

FAR 13.106-1(b) describes the documentation requirements for a sole-source acquisition when using simplified acquisition procedures up to the simplified acquisition threshold.  Follow these procedures when doing a sole-source acquisition when using simplified acquisition procedures up to the simplified acquisition threshold.

FAR 13.501(a) describes the documentation requirements for a sole-source acquisition when using simplified acquisition procedures for commercial items greater than the SAT and up to $7 Million (or $13 Million for acquisitions described in 13.500(c)).  Follow these procedures when doing a sole-source acquisition when using simplified acquisition procedures for commercial items greater than the SAT and up to $7 Million (or $13 Million for acquisitions described in 13.500(c)).  See also FAR 13.106-1(b)(2).

Link to comment
Share on other sites

ji20874,

Thanks for the response and for sake of my understanding...

Consider a 25k purchase of commercial items in which we are planning a single/sole source (the manufacturer of the item is the exclusive provider). 13.106-1 (b) (1) states that I have determined one source reasonably available (in this case because of patent rights). My next step is to prepare a justification stating 13.106-1 (b) as the authority.  Following the justification  I would post a combined synopsis/solicitation (for any time frame I deem reasonable meeting conditions at 5.203(b)) which would include the synopsis requirements at 5.207 as well as the justification citing the authority as 13.106-1 (b).

Because 13.501 (a) documentation requirements do not apply I would simply post an award notice following award which would not have to include the justification. 

I do not see anywhere where a notice of intent would be required... Is this true? and Does my scenario make sense?

Link to comment
Share on other sites

If your proposed contract action is expected to be $25,000 exactly, then synopsis is not required.  See FAR 5.101(a)(1), where synopsis is required for actions expect to exceed $25,000.

If synopsis is required (for example, if the proposed contract action is expected to be $25,000.01 or more), then FAR 5.207(c)(15) asks you to identify the intended source for a noncompetitive (sole-source) action.  FAR 13.106-1(b)(3) sends you to 5.102(a)(6), which requires the solicitation posting to include the documentation for the brand-name item, if the reason for the sole source is brand-name -- if the reason for the sole-source is not brand-name, then you do not have to include the documentation.

 

 

 

 

 