Reasonable Hourly Increments (T&M)


Acq_4_life

Recommended Posts

The Acquisitions Department awarded a time-and-material contract for project management support to be performed for a base and two option periods. When billing, the contractor invoiced for the exact time and hours that an employee worked. Is it acceptable for a contractor to bill in different increments, i.e. 5, 8, 12, etc., on a time-and-material contract? Is there language to support this and language to include in the contract that restricts the contractor from billing different increments?

Link to comment
Share on other sites

Paragraph (a) (2) of FAR 52.232-7, Payments Under Time-and-Materials and Labor-Hour Contracts, states that ?The amounts shall be computed by multiplying the appropriate hourly rates prescribed in the Schedule by the number of direct labor hours performed.?