jeff4757 Posted March 24, 2014 Report Share Posted March 24, 2014 Our company has a CPFF completion type contract and have experienced a cost overrun. I understand under this type of contract that additional incurred costs are allowable-without FEE of course. Is there a specific clause that cites this allowance and is there a specific format to request reimbursement of these costs? Thank you for any feedback. Link to comment Share on other sites More sharing options...
ji20874 Posted March 24, 2014 Report Share Posted March 24, 2014 See the contract clause at FAR 52.232-20 Limitation of Cost or at FAR 52.232-22, Limitation of Funds, whichever is in your contract. Link to comment Share on other sites More sharing options...
wvanpup Posted March 24, 2014 Report Share Posted March 24, 2014 Also try 52.216-8, Fixed Fee Link to comment Share on other sites More sharing options...