Sarah J Posted August 27, 2022 Report Share Posted August 27, 2022 We have been in closeout of a large CPIF & CPFF contract for years. We are down to our final element: Property. All property is identified on a number of DD1149s pending releasing PCO signature, or the DD1149 process could be skipped and the government could issue a unilateral mod providing transfer of the property off contract. We cant get either done and Closeout PoP end is rapidly approaching. As a contractor, do we have any leverage here?? Link to comment Share on other sites More sharing options...
bob7947 Posted August 31, 2022 Report Share Posted August 31, 2022 Can anyone help with this? Link to comment Share on other sites More sharing options...
Vern Edwards Posted August 31, 2022 Report Share Posted August 31, 2022 On 8/27/2022 at 8:06 AM, Sarah J said: We have been in closeout of a large CPIF & CPFF contract for years. We are down to our final element: Property. All property is identified on a number of DD1149s pending releasing PCO signature, or the DD1149 process could be skipped and the government could issue a unilateral mod providing transfer of the property off contract. We cant get either done and Closeout PoP end is rapidly approaching. As a contractor, do we have any leverage here?? Is it costing your company money? Link to comment Share on other sites More sharing options...
Retreadfed Posted August 31, 2022 Report Share Posted August 31, 2022 1 hour ago, Vern Edwards said: Closeout PoP end is rapidly approaching. What do you mean by "closeout PoP"? Also, why is this a problem for you? Link to comment Share on other sites More sharing options...
Neil Roberts Posted August 31, 2022 Report Share Posted August 31, 2022 On 8/27/2022 at 8:06 AM, Sarah J said: Closeout PoP end is rapidly approaching. As a contractor, do we have any leverage here?? If you really have a contract requirement to end all closeout work, you should consider stopping such closeout work as required by the contract. Would be prudent to notify the government with as much advanced notice as you can give, and ask for input from the government as to the interpretation that all closeout work is required to stop after that POP and that all work performed after that date is in jeopardy of not being paid by the government. Link to comment Share on other sites More sharing options...