neecai Posted April 20, 2009 Report Share Posted April 20, 2009 I am wondering if I award a Time and Material base ID/IQ contract, that when I have a specific task order to let, that I could request a quote for the specific SOW, and request a FFP for that order. Link to comment Share on other sites More sharing options...
formerfed Posted April 20, 2009 Report Share Posted April 20, 2009 I am wondering if I award a Time and Material base ID/IQ contract, that when I have a specific task order to let, that I could request a quote for the specific SOW, and request a FFP for that order. Yes, assuming that the ordering provision (and any other pertinent clauses) allows FFP orders. If not, you may have to negotiate a revision to the contract to allow it. Link to comment Share on other sites More sharing options...