Jump to content

Search the Community

Showing results for tags 'miller act'.

  • Search By Tags

    Type tags separated by commas.
  • Search By Author

Content Type


Forums

  • Instructions and Terms of Use
    • Terms Of Use
    • Before You Register, Before You Post, Instructions for Writing Your Question
  • Contracting Forum
    • What Happened?
    • Polls
    • For Beginners Only
    • About The Regulations
    • COVID-19 And Its Effect on Contracting
    • Contracting Workforce
    • Recommended Reading
    • Contract Award Process
    • Contract Pricing Including CAS & Allowable Costs
    • Contract Administration
    • Schedules, GWACS, MACs, IDIQs
    • Subcontracts & Subcontract Management
    • Small Business, Socioeconomic Programs
    • Proposed Law & Regulations; Legal Decisions

Blogs

  • The Wifcon Blog
  • Don Mansfield's Blog
  • Government Contracts Blog
  • Government Contracts Insights
  • Emptor Cautus' Blog
  • SmallGovCon.com
  • The Contractor's Perspective
  • Government Contracts Legal Forum
  • NIH NITAAC Blog
  • NIH NITAAC Blog

Calendars

  • Community Calendar

Product Groups

There are no results to display.

Categories

  • Rules & Tools
  • Legal Opinions
  • News

Find results in...

Find results that contain...


Date Created

  • Start

    End


Last Updated

  • Start

    End


Filter by number of...

Joined

  • Start

    End


Group


AIM


MSN


Website URL


ICQ


Yahoo


Jabber


Skype


Location


Interests

Found 2 results

  1. Earlier this year the ASBCA concluded that the Christian Doctrine applies to performance and payment bond requirements. The case involved the construction of a pre-fab building. The CO used a GSA schedule contract to make award. The order did not include FAR 52.228-15, which implements the requirement for performance any payment bonds. Upon award the CO requested bonds. The contractor initially said it couldn't provide them, but ultimately did two years later! Upon providing the required bonds the CO provided equitable adjustment to compensate the contractor for the bonds that it said were to have been read into the contract to begin with. Upon completion of performance the contractor submitted a claim for delay costs among other things due to the two years that had passed between award and performance. One of the arguments the contractor made was that this was not a commercial contract and not a construction contract, so bonding wasn't required. The Board concluded the contract was for construction and that the Miller Act requirements still applied, even if the procurement was conducted as a commercial acquisition. The Board determined that inclusion of the clause was mandatory, even though the bonds statutes and implementing FAR regulation permit the CO to waive bonding. They reasoned that the CO could only waive the requirement in situations explicitly stated in the statute, which did not apply in this case (i.e., performance in a foreign country or authorized by another statute). The Board also concluded that bonding requirements are significant components of public procurement policy. In the request for reconsideration, the contractor cited a prior U.S. District Court case (Faerber Electric) as having held that the Christian Doctrine does not apply to the Miller Act. The Board distinguished this case from Faerber. It stated that the decision in Faerber was in the context of whether or not a subcontractor possessed a right of action against a prime contractor based on the presumption that the prime was required to have obtained a payment bond, despite both the CO and contractor having ignored the requirement. It also stated that Faerber did not decide address applicability of the Christian Doctrine. ASBCA Opinion http://www.asbca.mil/Decisions/2017/60686, 60687 K-Con, Inc. 1.12.17.pdf Request for reconsideration denied. http://www.asbca.mil/Decisions/2017/60686, 60687 K-Con, Inc. 5.8.17.pdf Prior related Wifcon discussion.
  2. I have been advised that an emergency construction contract for forest debris removal was awarded (>$150K) and the contractor began performance without providing bonds IAW the Miller Act. The contract did not contain a requirement to provide bonding and the work is currently in progress. The Miller Act requires that payment and performance be submitted before receiving a notice to proceed with the work or being allowed to start work. I believe this could be corrected by modifying the contract bi-laterally to require bonding IAW the Miller Act and allow the contractor to submit a payment request for the actual cost of the bonds. Question: Can the government require the contractor to provide bonding after the fact? Question: Is the Miller Act subject to the "Christian Doctrine"? Comments are appreciated.
×
×
  • Create New...