Jump to content
The Wifcon Forums and Blogs

here_2_help

Members
  • Content count

    1,747
  • Joined

  • Last visited

Community Reputation

0 Neutral

1 Follower

About here_2_help

  • Rank
    Platinum Member
  • Birthday 12/17/1960

Profile Information

  • Gender
    Male
  • Location
    SoCal
  • Interests
    No special interests, really. Kind of a jack-of-all-trades/master-of-none kind of person.

Recent Profile Visitors

33,817 profile views
  1. Invoicing for unworked hours under a FFP TO

    Not sure the fault lies fully with the contractor on this one.
  2. Tracking LOE in FFP subcontracts

    My opinion is that you made a poor choice in selecting the subcontract type. My opinion is that you used a subcontractor to bypass your prime contract LOE restrictions, and the COR caught you doing so. Too late to change the subcontract now, I guess. In future, similar, situations you may want to consider a Fixed Unit Rate subcontract where each day has an associated FFP amount and each day counts as 8 hours against your LOE restrictions.
  3. FFP Contract Maximum Increase?

    When you prepare your J&A, will you note that market research shows that Contractor2 can supply the item(s) required, and that Contractor1 is no longer the sole source?
  4. Sounds to me like the prime wants your commissions to be a direct cost of its contract; hence it names you subcontractor. I agree with the others that that designation does not necessarily make sense.
  5. FFP Contract Maximum Increase?

    Who is the customer for Contract1? How does the contractor get paid? Does it get paid for orders on its ID/IQ contract that were placed by Contractor2? I'm guessing that once the contractor has fulfilled its maximum under Contract1, it's done. It doesn't matter who ordered what. If so, then if the customer has additional demand then it needs to add funding to Contract1. Period. Or the customer can go to Contractor2 and order items and pay for them. Should be the same result if I've parsed the situation correctly. Either add funding to Contract1 or else use that funding to buy from Contractor2.
  6. The question I would ask myself is what recourse the prime has, if I do not accept the prime's offer? If the prime can go elsewhere I might make a counter-offer closer to what my break-even rate is. If the prime cannot go elsewhere then I might simply reject the offer and ask to speak to the prime's small business liaison officer about the unreasonable offer.
  7. The contractor Business Systems oversight regime is flawed. It was flawed when the DAR Council implemented it in 2011 and it's still flawed today. One of the flaws is that "acceptable" and "approved" are synonyms, just like "unacceptable" and "disapproved" are synonyms. (Primarily turns on which system is being discussed). Officially, DCMA is responsible for reviewing/assessing three systems (Purchasing, Property Control, EVMS) and DCAA is responsible for auditing/assessing three systems (Accounting, Estimating, MMAS), but of course the cognizant ACO/DACO/CACO makes the official determination. (See DCMA Instruction 131). Government reviewers have been evaluating property, purchasing and estimating systems for as long as I've been in this crazy business. I've never experienced--or even heard of--a contractor pushing back, asserting that the government lacked authority to perform those reviews. I believe a contractor would be afraid to make that assertion, fearing what the repercussions would be. Easier to staff up (typically on overhead) and support government reviews. And then pass on the additional expense to the buying commands. Per DCMA Instruction 131 (at 3.1.2)
  8. Vern, we disagree regarding the importance of employee morale. We disagree that morale is unimportant, or that it can be affected by little things, such as providing disposable plates and plastic silverware. We disagree that the Department Defense is suffering from a loss of cutting edge technology, as so many bright young folks opt for high-tech jobs in places such as Silicon Valley instead of joining the Federal civil service or joining a government contractor in a research & development capacity. We disagree that this little thing, this ankle-biter of a decision, doesn't matter. Because I believe that it does matter. It's a symptom of something bigger. If the Department of Defense ever wants to regain its high-tech leadership, if it ever wants to start attracting the next Feynman, then it needs to address these sorts of things. Young people with STEM degrees have options, and right now working for the DoD is close to the bottom of their list. Don't take my word for it. Any Google search will turn up lots of citations discussing industry's anxiety about where the next generation of STEM employees are coming from.
  9. There is no FAR clause, but there is a DFARS clause. 252.242-7005. It requires the contractor to have an adequate purchasing system, if any awarded contract contains the DFARS clause 252.244-7001. 252.242-7005 specifies the remedy for any business system that is found not to be adequate. There is a mandatory payment withhold.
  10. A couple of thoughts. Take 'em for what they may be worth. 1. The contractor has already (or will be very very soon) prepared an official corrective action plan with milestone dates. It's what happens when a contractor business system gets disapproved. The cash flow impacts imposed by the government on large prime contracts awards tends to ensure that the contractor implements the CAP with a sense of urgency. 2. The timing of when the CPSR team returns for a re-review and re-assessment of the system approval is not within the control of the subcontractor. Any milestone date they would provide would be a guess, at best. 3. You are concerned about a focus on trying to regain approval of the purchasing system negatively impacting the focus on subcontract performance. So why in the world would you want to impose additional burdens on the subcontractor at this time. Why would you want to have the company submit another CAP to you and have them attend meetings with you to monitor progress? Isn't that counterproductive to your concerns? 4. The subcontract you awarded contains all remedies for late performance or non-performance. I would suggest that unless you have terms that permit you to do what you want to do (i.e., request a CAP and monitor progress against the CAP), you refrain. You might find yourself with a REA or claim submitted for the additional costs associated with your additional requirements. 5. Further, you cannot transfer performance risk to subcontractors. You, as prime, are already responsible for contract performance to your government customer. The most you can do is to sue the subcontractor or impose liquidated damages (if permitted by your subcontract). 5. What, specifically, are the risks you are trying to mitigate by imposition of additional requirements? If the issue is a critical item such that a second source is not feasible, then you already had the risk of non-performance yesterday before the subcontractor's purchasing system was disapproved. What has changed? Nothing. If the subcontractor's performance is critical to your program performance, and you weren't already monitoring your subcontractor's performance yesterday, why is today going to be different? Despite Neil's comments I think you are very much overreacting. If nothing else, you are stepping into the government's role of reviewing, assessing, and determining the adequacy of the subcontractor's purchasing system. Why in the world would you want to do that? Do you also want to audit the subcontractor's final billing rate proposal on behalf of the DCAA? (See the LMIS ASBCA decision from December 2016.) Again, just my point of view.
  11. Adding to Vern's questions -- What are your concerns? What risks do you see, against which you would like assurance? Fundamentally, I don't see ANY ADDITIONAL way to "ensure performance" because any contract/subcontract you have already awarded requires performance. Do you think another signed letter is somehow going to reduce the risk of nonperformance? I don't think so. I'd like you to answer Vern's questions so I know where you're coming from, but I don't think you're going to get to where you say you want to go. +++ Let me add that contractors fail CPSRs frequently. Sometimes for tickey-tack reasons and sometimes for very valid systemic reasons. It happens; and it happens to the biggest contractors as well as the smaller contractors. Not much changes, except for consent requirements. Plus the contractor then dedicates a portion of its purchasing team (and leadership team) to developing and executing a corrective action plan, instead of spending time doing purchasing.
  12. Tracking LOE in FFP subcontracts

    This doesn't strike me as an unreasonable request. You have a CPFF Term contract. To augment your workforce you engaged a consultant. The COR wants you to track the consultant's labor hours as if they were your own labor hours and count them as if they were your own labor hours. The fact that you awarded a FFP consultant subcontract would seem to be irrelevant. (It might also be unreasonable in certain circumstances. What if the consultant finished the subcontracted work in half the expected time?) Why are you pushing back so hard? What don't you want the COR to know?
×