The Councils' response was as follows:
(See FAR Case 2008-012, Clarification of Submission of Cost or Pricing Data on Non-Commercial Modifications of Commercial Items (75 FR 13414)).
My initial reaction was "Good, they got it right." However, I was not satisfied with the complete lack of explanation other than that this information was "commonly understood." "It is commonly understood?" is the equivalent to saying "Well, everybody knows?", which is not an answer that I would accept from a student nor is it one that the public should be accepting from the FAR Councils. Further, the FAR Councils' use of "commonly understood" raises the question: Commonly understood by whom? Based on my experience, "commonly debated" would be a more apt description.
Task and Delivery Orders are "Contracts"
By stating that TINA applicability determinations must be made at the task and delivery order level, the FAR Councils have, perhaps unwittingly, admitted that task and delivery orders are "contracts" as defined at FAR 2.101. Consider the requirements for obtaining cost or pricing data at FAR 15.403-4(a)(1):
If TINA applies to task and delivery orders, then task and delivery orders must fall into one of the three enumerated categories. A task or delivery order issued by the Government is certainly not a subcontract, so (ii) is out. A task or delivery order under a contract is not a "written change in the terms of a contract", so they do not meet the definition of "contract modification", thereby eliminating (iii). Thus, task and delivery orders must be "contracts."
However, one cannot reasonably describe this information as "commonly understood" either. Consider the following statements made in FEATURE COMMENT: Contesting Task And Delivery Order Awards At The COFC--Policy Implications Of A Choice Federal Courts May Soon Have To Make (51 NO. 20 Gov't Contractor ? 174). In discussing the automatic stay provisions of CICA, the author writes:
The author, seemingly indecisive, also writes:
This author is not alone. In FEATURE COMMENT: Acquisition Reform Revisited--Section 843 Protests Against Task And Delivery Order Awards At GAO (50 NO. 9 Gov't Contractor ? 75) the authors put forth the following argument:
I agree with the first author's assessment of the potential controversy that would ensue if the FAR Councils were to redefine "contract" to include task and delivery orders. If the FAR Councils were to propose such a rule, I would estimate that they would receive no less than 100 public comments.
Where's the Cost or Pricing Data Clause for Task and Delivery Orders?
If it's "commonly understood" that TINA applies to task and delivery orders, why isn't there a standard FAR clause for use in task and delivery order contracts that compels the submission of cost or pricing with a task or delivery order proposal when applicable? There's a standard FAR provision at FAR 52.215-20, Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing Data (Oct 1997), that can be used to compel offerors to submit cost or pricing data when submitting offers for a basic IDIQ contract. There's also a standard FAR clause at FAR 52.215-21, Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing Data?Modifications (Oct 1997), that compels submission of cost or pricing data when pricing contract modifications (if applicable). Where is "Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing Data?Task and Delivery Orders"? Why not have offerors agree to submit cost or pricing data (if applicable) with subsequent task and delivery order proposals?
TINA Yes, CAS No
The Councils' response in the publication of this rule reminded me of an earlier response pertaining to the applicability of CAS to task and delivery orders accompanying a final rule on CAS (70 FR 11743-01). In that response, the Councils reached the opposite conclusion. The exchange was as follows:
Thus, a determination of CAS applicability is made only when placing the basic IDIQ contract. If an IDIQ contract is subject to CAS, all orders under the contract are subject to CAS. If an IDIQ contract is not subject to CAS, none of the orders under the contract are subject to CAS.
So, according to the FAR Councils, a contracting officer must determine applicability of TINA when awarding a basic IDIQ contract and issuing any subsequent orders, but need only determine the applicability of CAS once?when awarding a basic IDIQ contract.
This raises another yet another question?how is a CO supposed to know this? Consider the rules for determining CAS applicability at 48 CFR 9903.201-1:
By asserting that CAS determinations are not made at the task or delivery order level, the FAR Councils must be using a definition of "contract" that is different than what appears at FAR 2.101. What definition are they using and why does that definition exclude task and delivery orders? I don't get it.
Recommendation
If the FAR Councils believe that task and delivery orders are "contracts" as defined at FAR 2.101, then they can clear up a considerable amount of confusion by including these types of orders in that definition. If they do that, why not add a standard FAR clause compelling submission of cost or pricing data (when applicable) with task or delivery order proposals? While they're at it, how about an explicit statement in the FAR stating that TINA applicability determinations are made at the task and delivery order level and another statement that CAS applicability determinations are not? Probably too much to ask.
- Read more...
- 8 comments
- 10,431 views