All,
There is a discussion in my office on the correct path to increase the estimated cost (and funding) on a CPFF contract that is going to eventually exceed the estimated cost in order to complete. In this case, there has been no Government-directed change in the requirements. It is an R&D completion contract that, due to some performance complications, cost more than was competitively proposed and the Government wants to continue to fund to have an executable program. The LoF clause says that the estimated cost must be increased as well. So, the office discussion has revolved around what is needed to continue to incrementally fund the contract.
One thought is the contractor submit a ROM to the PCO to and all parties sit down and determine if the new estimated costs to complete is within the programs budget/schedule to continue. If so then we increase the estimated costs and continue to incrementally fund and if not then we terminate the contract.
A second thought was the contractor submits a proposal and all costs are evaluated and once agreed the estimated costs to complete are increased and we incrementally fund. Some pushback with this is schedule. The program cannot afford the additional time to have a completed program as it puts other missions at risk. Second, is the understanding of FAR 15.403-2(b) which states "Certified cost or pricing data are not required for proposals used solely for overrun funding or interim billing price adjustments." If they aren't required to certify does a proposal add more value then a ROMN if the Government can still feasibly determine its in the best interest to move forward.
So, I thought I'd come to this board to discuss/receive feedback and see if I can get some other opinions. Thanks.