  1. I have an TO placed against an IDIQ. The TO was awarded at a total cost of $288K. The agency wants to do an in-scope change to increase funds, which will, one, complete the work currently being done, and two, add additional work related to the same work being performed now. The agency says that when they submitted the SOW for the current contract, they under estimated the amount of hours needed to complete the work. The amount of the in-scope change is $300K. Can I do an in-scope change, with an amount larger that the award amount, or should I just do a new TO against the IDIQ?
×
×