  1. I would give serious consideration to a hybrid, service/construction, FFP/cost reimbursement, contract that would give your COR the right at a price level to authorize certain emergency actions to be completed. Above that threshold, a KO/CO would get a proposal from the contractor. Several Maintenance Contracts have this contingency option. This contract is competed at the onset and thus when emergencies arise you only deal with one contractor. These have separate levels of emergencies that are regularly dealt with on a separate CLIN. I assume you have enough history on that base for certain type actions, thus necessitating a certain response time to certain type emergencies. Don't pigeon hole these type of actions to simply IDIQ type contracts. Think outside the box.
×
×