I just inherited a $1M generator installation contract. Period of performance April 2019-April 2020. In Sept 2020 a suspension of work was issued due to government delay for various reasons...change of generator locations, change orders, and lack of customer communication and decision making. 10 months later - I am in the process of lifting the Suspension. While I have read the clause and understand the GC cost excluding profit. Will the subcontractors be due any consideration for the delay? Demobilize/ Mobilize, increase in material cost, etc. Any guidance is appreciated.
IAW 52.242-14
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1)by an act of the Contracting Officer in the administration of this contract, or (2)by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.