  1. Help!!  I've got two sources telling me two completely different things with regard to 52.215-12 on a large dollar FFP contract.  One source says that even though 52.215-12 does not apply to us as we bid this competitively, that it does apply to any Subs/Vendors if those Subs/Vendors were not competitively bid.  The other source says that since 52.215-12 does not apply to us as we were competitively bid, that it also does not apply to our Subs/Vendors.  Who is right in this situation?  

     

      

     

  2. I have a vendor that is doing some dip-coating on a program through one of our higher tier vendors.  The higher tier vendor asked if the dip-coating company was ITAR registered and they are not - they are a small job shop.  The Prime contract is subject to ITAR but does that mean this 3rd tier vendor needs to be?  He's doing standard dip-coating on supplied parts, he isn't making the parts, just dip coating them to specs as provided.

  3. 4 hours ago, Vern Edwards said:

    I think that what you want to know is: Under the law, can a company in the United States refuse to accept a DPAS rated order from a government contractor?

    Is that your question?

    Vern, YES!  That's exactly what I am wondering. Thanks!

  4. Can a Contractor reject or not accept the award of a Purchase Order from a Government Prime Contractor even if their quote is still valid?  The work is under a DoD contract and being awarded by a Gov't Prime Contractor to a lower tier Contractor.  The PO is under a DO-rated order as well.

×
×