  1. I am trying to find out when/if a PLA is applicable. I understand that PLA's may be done prior to solicitation if a construction project is over $25m. We are having an internal debate if an 8(a) IDIQ construction services contract (value $70m) with no task orders that will exceed $25m, if PLA needs to be addressed. One contention is the IDIQ contract will be for $70m and PLA should be addressed. Another contention is the value of the IDIQ contract should have no bearing on it since the task orders are what funds the construction contracts and none of the task orders will be over $25m. Any assistance would be helpful.
×