Everything posted by JMG

  1. Sale of Government Property

    Navy is experience the same asset management policy, but I think the AF is ahead of the game. FIAR is a huge focus now. It will be interesting to see how it evolves and if it makes it way into acquisition regulations. This is an interesting post. Thanks for sharing. Please keep us posted on the strategy you take.
  2. Thanks Todd. So I hope we have answered the OP's question.
  3. Vern covered this politely in his last post, and I am surprised he did.... By this rationale, a contractor can enter into a FFP arrangement with the Government, for an agreed to price, then switch every labor category on which that FFP was based. Also, by this rationale, as long as the contractor is conforming to any labor mix within the SCA WDs, they can request a price adjustment to the contract without previous CO review and approval of the deviations. I don't think that's a good business deal for the Govt, do others? Please let me know if I am off here! I'll own up to it.
  4. Do you consider the added labor categories out of scope of the contract or the original competition?
  5. Thanks Vern. Would another example of standards, taken from the DOD Source Selection Procedures, be relevancy of past performance (p.27) ? The standards for relevancy being : Very relevant; relevant; somewhat relevant; not relevant (setting aside your opinion of the document) Ref: https://acc.dau.mil/docs/DoDSSP/Source%20Selection%20Guide%20and%20Memo%201%20April%202016%20ljm.pdf
  6. Just a note: other observers are interested on how ji20874 is executing past performance evaluation without standards in his office. A method was mentioned by another post, but I think it is worth further discussion. Thanks.
  7. Olga- What does the CPFF CLIN state? Are the estimated costs and fee specifically identified?
  8. Vern, Great perspective. You state: If anyone believes that better contract performance management yields better results and is looking for more resources to devote to that work, start by seeking the elimination or moderation of the multiple-award preference. Do you have any resources or recommendations where one (in the Government) can go to get information on how to better manage contract performance? Thanks
  9. 3 Day Congressional Notification-then no award?

    If you are talking about not awarding immediately after the 5PM posting ? Yes, I have heard of that.
  10. He is an O-10. I'm pretty sure he understands how acquisition works. Army's Program Managers are O-5s. We have a requirements problem. Again.
  11. “We are not talking about nuclear subs or going to the moon here. We are talking about a pistol.” Said the General (the requirements lead)
  12. $365 M, for what appears to be a commercial item, and two years of testing? Terrible.
  13. The solicitation states LPTA for award of multiple contracts? Or the task orders will use LPTA procedures?
  14. Curious for feedback... Does settlement at a bottom line price, of a sole source contract over the TINA threshold, impact the reliability of a defective pricing claim? FAR 52.215-10(c)(1)(iii) states the contractor cannot use agreement on total cost as a defense, but what about total price (when profit was not specifically agreed to)? Any pertinent case law would be appreciated. Thank you.
  15. I don't think its a good defense, but I am just posing a question to what the defective pricing clause states. It must state total cost, and not total price, as an invalid defense for a reason? Why not total price or total cost? It's a FAR based question. I get all the answers- all good. Good discussions. Thanks.
  16. I appreciate the references and burden of proof requirements. Any opinions, or experience, with the posed question. I like how Vern phrased it: "What do you think? Since the defective pricing clause does not prohibit a "bottom line price" or "total price" defense, can a contractor defend itself against an accusation of defective pricing and false claim by saying that the parties agreed on a bottom line/total price"?
  17. Thanks Help. Interesting. So DCAA will still review but just provide objective results? I tend to think DCMA lacks the local knowledge to perform such reviews; they would have to reach out to a cost/pricing center or other team (similar to CPSR).
  18. Can you qualify this? I understand it to be that, while DCMA has determination responsibility, they rely on DCAA to perform the review and compliance. At least in my recent experience.
  19. Weather window? Is this construction?
  20. If it is going to competitive, and you believe the preparing contractor will propose, why would you let that happen? Has market research been conducted? Under what contract vehicle is said contractor writing your SOW? You may have an Agency OCI clause in that contract which backs your intuition.
  21. Contract Level Funding

    brent- Ask your DCMA CA. You might get invoice/voucher/ financing rejections when your contractor bills. You will then have to do a contract mod. DFAS is really strict on payment instructions per the PGI 204.7108 . Also see PGI 204.7103
  22. Cost Realism

    Michael700- Agreed. This approach should not be used to developmental or complex acquisitions. For A&AS where its CPFF LOE where the solicitation of provides the estimated hours and labor mix, it is a sound approach; and supported by GAO if you read the case.
  23. Cost Realism

    Possible, but you how could you determine the costs are unrealistically low in this manner? I don't think, as long as you are consistent, the realism analysis would be successfully protested. It would be a reasonable and realistic representation of what the market offered.
×