Jump to content
The Wifcon Forums and Blogs

jmsmith

Members
  • Content Count

    10
  • Joined

  • Last visited

Community Reputation

0 Neutral

About jmsmith

  • Rank
    New

Profile Information

  • Gender
    Male
  • Location
    Atlanta, GA

Recent Profile Visitors

1,822 profile views
  1. Thanks for the quick responses, this is all excellent reading and exactly what I couldn't find yesterday.
  2. All, I've been doing some searching and coming up empty handed. I'm looking for cases/examples of a COR directing the contractor to make a change, the contractor proceeds to make the change (and the government benefits), all the while knowing the COR (or should have known) had no authority to direct the change and the courts find in favor of the government. I've heard contracting officers say they wouldn't play a claim under the above circumstances because the contractor knew the COR wasn't authorized to modify the contract. However, I was reading MA DeAntley Construction V. US No. 04-1052C
  3. Joel, when you said "in your experience the local customer either didn't know, or didn't bother to pursue finding the expired funds", then was the mod execute with current year funds or was the mod not executed unless they could come up with expired funds from the year the contract was awarded? Unfortunately, I have two different finance offices suggesting two different things. Ultimately everyone, including legal, will be around a table to ensure no rules/laws are being broken. I'm not a finance person and was merely trying to get a little smarter on it. Thanks
  4. Fair enough and you are more than likely correct. However, theoretically, if the funds are not available for whatever reason, what are the next funds that should be used to fund an in scope mod? Current year? Could it be any year, available O&M funds from between the year of award to the current FY? Thanks for the replies.
  5. They are "not available" for some other reason, it's not entirely clear why from where I sit but local agency indicates they can't get O&M funds from FY08. The thought was they can use current year funds to cover the in scope modification but a question was raised as to whether or not they could use available expired funds from either FY09 or FY10. I thought I had read in a fiscal law course that funding for an O&M in-scope mod must first come from the year in which the contract was awarded and if not available, then from the current FY year. I may have misunderstood. The above is t
  6. Basic question and for the life of me I can't find the answer in the Red Book or Agency regulations. Scenerio is an FY08 O&M renovation. An inscope modification has come up and FY08 expired funds are not available. Must FY11 O&M funds be used, or could FY09 or FY10 expired O&M funds be used? FY09 and FY10 funds were used previously to fund inscope mods that occured in those respective years when FY08 funds were not available. Can you point me to the guidance?
  7. In reference to FAR 36.203(a): "An independent Government estimate of construction costs shall be prepared and furnished to the contracting officer at the earliest practicable time for each proposed contract and for each contract modification anticipated to exceed the simplified acquisition threshold." There is debate in my office as to whether the "anticipated to exceed the SAT" applies only to the modification portion of the sentence or to both the proposed contract and modification portion. Do we need an IGE for a small construction contract that is not anticipated to exceed the SAT? Than
  8. Thanks for the feedback all. You've solidified much of what I was thinking. This is not ECI Joel, but a similar variant.
  9. Thanks for the reply. I gather you are saying if we wanted to do this, we would have to set it up at the outset the way you are describing? We have an ongoing debate and some have interperted 52.216-17(g)(1) as allowing the government and contractor to bilaterally agree to remove portions of the work to negotiate separate disposition of that work, completely removing it from the FPI(S) operation (to include negotiating a FFP profit for that piece of removed work). Adjusting the targets on the work that remains FPI(S) would be easy enough. Would this seem even plausible to you? Thanks again
  10. We have an construction contract with 2 CLINS. CLIN 1 is a FFP clin for the construction contractor to provide preconstruction services during design. CLIN 2 is an FPIS clin to actually build the facility being designed. The design packages are phased such that the construction contractor can start working prior to the whole design being completed. As the individual design packages are completed to 100% we are wanting to convert that portion of the work from FPIS to FFP, while leaving the remaining portions of work, still being designed, as FPIS (no work is happening on the portions that ar
×
×
  • Create New...