Jump to content

NYR

Members
  • Posts

    4
  • Joined

  • Last visited

Everything posted by NYR

  1. Yes, the scope of the next contract was reduced to reflect funding limits imposed by the program office's funding source and guidance on the appropriate level of services. The contract, as in Arko, was for guard services.
  2. Vern, thanks for answering so promptly. As a frequent lurker here and reader of the source selection answer book, I care what you think ;D I read primarily Arko Executive Services, Inc. v. U.S., 553 F.3d 1375 (C.A.Fed. 2009) which is the appeal from the final order in 78 Fed. Cl. 420. I will incorporate In re Griffin Services in the analysis.
  3. Also, another way to ask the question: Does an agency have to exhaust all available options under a contract before exercising a 217-8 extension?
  4. Question: Can a CO exercise 52.217-8 at the expiration of an option year when there are available future option years left on a contract but not enough funding to exercise future option years? Scenario: Contract for services had 1 base year and 4 option years. The base year was performed and the CO exercised the first option year. At the end of the first option year, the CO was informed by the program office that sufficient funding was not available for a 2nd option year. The contract was going to expire and the CO did not have a replacement contract in place. The CO did not have adequate time to award a replacement contract. The CO began the procurement process for a new contract. During that time, the CO exercised the clause 52.217-8 a total of 5 times, first for 2 months, then 4 more exercises of 1 month each, totaling 6 months. The clause was unmodified from the version provided for in the FAR. Discussion: The CO contends that this is a valid exercise. FAR 17.207 states, among other things, that the CO "may exercise options only after determining that -- (1) Funds are available." Funds were not available for the 2nd option year, so the CO could not have exercised the 2nd option year. If a future option year cannot be exercised, the contract will expire at the conclusion of the current period of performance (in this case, the POP was defined in the option year 1 CLIN). FAR 37.111, Extension of services, permits the CO to include an option clause described in 17.208(f) "which will enable the Government to require continued performance of any services within the limits and at the rates specified in the contract" noting that "award of contracts for recurring and continuing services are often delayed due to circumstances beyond the control of contracting offices". FAR 17.208(f) states to insert a clause substantially the same as 52.217-8, Option to extend services, "in contracts for services when the inclusion of an option is appopriate" While FAR 37.111 provides examples (bid protests, alleged mistakes in bids), those examples are not exhaustive. Rather, the requirement seems to be whether an 'award for a contract for recurring and continuing services was delayed due to circumstances beyond the CO's control'. Vern Edwards published two articles in the Nash & Cibinic Report in June 2007 "When the Government can choose among options: let the contractor beware" and November 2007 "Postscript: When the Government can choose among options" (21 N&C 6 and 21 N&C 11, respectively). In the first article, Vern describes a contract very similar to what I mention above. In that case, the "Government exercised the first three options, but during the third option term (fourth contract year), the Contracting Officer notified the contractor that instead of exercising the fourth extension option the Government would exercise its option under the clause at FAR 52.217-8 ... and conduct a new procurement." Later in the article, Vern states "it appears that the clause is intended to be used as a stop-gap measure when circumstances beyond the control of the contracting office delay the award of a new contract. But in this case, the matter was entirely within the control of the contracting office, which chose not to exercise the FAR 52.217-9 option." In the second article, Vern wrote that "the FAR 52.217-8 option clause is for use at the end of a contract when the award of a new contract is 'delayed due to circumstances beyond the control of contracting offices.'" Taking the FAR provisions, articles, and decsisions together, I think it's plausible to distinguish my hypothetical with the one in the article. In the present fact pattern, the CO did not have the authority to exercise 52.217-9 and doing so was not within the CO's control or discretion. The contract was nearing its end of the POP, even though there were future option years. Under those circumstances, is it reasonable and permissible for the CO to use 52.217-8 as a stop-gap to get a new solution in place, even though the contract had future option years? Thank you in advance. I can answer questions or provide more details if necessary.
×
×
  • Create New...