    GAO Protest Denied - Period of Performance Ext

    The stop order has been lifted and the contractor has resumed set up and operation of a base supply store. Orders are being placed against a BPA using FAR 8.405.
  2. Upon award, a GAO protest was received and inevitably denied. In all, 94 days of performance were lost due to the stay imposed by GAO. Can the Govt mod the contract to get that time back? If so, would the period of performance simply change to a negotiated start date and all other performance periods (opt. 1-4) change with it?
×