GSA Federal Supply Schedule Description Too Limited For Contractor to Receive Award

Sign in to follow this  
Centre Law & Consulting

60 views

In its September 18, 2017 decision, the GAO sustained a protest over a task order awarded to a contractor whom only had one of the two required services listed on their General Services Administration (“GSA”) Federal Supply Schedule (“FSS”).

The United States Navy attempted to acquire 120-250 hotel rooms for civil service mariners in the Norfolk, Virginia area. The Agency invited vendors to submit offers through the GSA’s e-buy system, with instructions to only submit services on a current GSA Schedule contract. Unfortunately for the awardee, the request for quotation (“RFQ”) also required shuttles from the hotels to the work sites.

While the decision takes pains to describe in detail the intricacies of GSA Schedules, the result is simple. The original awardee simply did not have transportation services included as “additional services” as required. The RFQ listed two separate tasks orders, one of which was transportation by shuttle. Despite the awardee’s ability to provide these services, the RFQ clearly emphasized the award would be made exclusively through the GSA thereby excluding companies without all required services listed on the Schedule.

About the Author:

Tyler Freiberger Headshot | Centre Law & Consulting in Tysons, VA Tyler Freiberger
Associate Attorney

Tyler Freiberger is an associate attorney at Centre Law & Consulting primarily focusing on employment law and litigation. He has successfully litigated employment issues before the EEOC, MSPB, local counties human rights commissions, the United States D.C. District Court, Maryland District Court, and the Eastern District of Virginia.

The post GSA Federal Supply Schedule Description Too Limited For Contractor to Receive Award appeared first on Centre Law & Consulting.


View the full article

Sign in to follow this  


1 Comment


Recommended Comments

If this was truly a case of the GSA FSS description being too limited, no contractor with that Schedule would be able to complete the work requested by the Navy.  The Navy should probably not have used the Schedules for this acquisition and if they had done proper market research they would have been able to determine that. 

Share this comment


Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×