In a GAO decision released September 13, 2017, the GAO denied Walker Development & Trading Group, Inc.’s (“Walker”) request for reconsideration of the denial of its costs.

On January 2, 2017, Walker filed a protest arguing that the Department of Veterans Affairs (“VA”) did not properly set a requirement aside for small businesses. In the VA’s report, the contracting officer stated that, after performing market research, she did not have a reasonable expectation that two or more capable small businesses would submit offers.  The GAO subsequently requested additional information on two potentially capable small businesses. Before filing its supplemental report at the request of the GAO, the VA advised the GAO that it intended to take corrective action. As such, the GAO dismissed the protest as academic.

Walker subsequently filed a request that it be reimbursed its costs of pursuing the protest by asserting that it was clearly meritorious and that the agency unduly delayed taking corrective action. The GAO denied Walker’s request, finding that the protest allegation was not clearly meritorious as the resolution of the protest required further record development.

Walker has then requested reconsideration of the GAO’s denial of its costs. However, in order to prevail on a request for reconsideration, a party must set out the factual and legal grounds requiring reversal and the party must specify any errors of law made or information not previously considered.

In its request for reconsideration, Walker argued that the decision contained a legal error as the GAO did not consider whether the VA unduly delayed in taking corrective action. However, as the GAO noted, in order to prevail in a request for reimbursement of costs, the protestor must show both that its protest was clearly meritorious and that the agency unduly delayed in taking corrective action. As Walker already failed to demonstrate that it was clearly meritorious, the GAO did not need to reach the decision as to whether the VA unduly delayed taking corrective action.

About the Author:

Heather Mims | Centre Law & Consulting in Tysons VA Heather Mims
Associate Attorney

Heather Mims is an associate attorney at Centre Law & Consulting. Her practice is primarily focused on government contracts law, employment law, and litigation. Heather graduated magna cum laude from the George Mason School of Law where she was the Senior Research Editor for the Law Review and a Writing Fellow.

The post An Agency Taking Corrective Action Does Not Necessarily Mean You Will Receive Your Protests Costs appeared first on Centre Law & Consulting.


View the full article

Sign in to follow this  


0 Comments


Recommended Comments

There are no comments to display.

Guest
Add a comment...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...